EMINENT DOMAIN    -  
                1180 Easton Rd Roslyn  
 The taking by our Township officials  
				of a resident's property  
                  
                
                
                The lawsuit for the taking was relinquished by vote 5-12-11.  
				No sooner did they put this issue down then they attempted to 
				obtain, with a portion of the leftover funds from this, the bank 
				building across the street ...... 
				
				5-12-11  A declaration of relinquishment  was before 
				the Board  - ( 9 yes)(3 no  
				Kline, Schreiber & Benzak ) and (1 abstention. M O'Connor )  
				So the project will be dropped .  They had til May 22nd to 
				decide - you have 2 years from the time if the "taking" to 
				decide to relinquish your claim. The Eminent Domain process  
				on this property  has been in litigation for 2 years 
				because the owner did not acquiesce.  Because the 
				litigation can conceivably get drawn out for much longer  - 
				and because the funds we had obtained may run out by then , or 
				funds that also might be possible require firm deadlines for the 
				start of the project, which can't be promised , it leaves the 
				question of  funding completely  unclear .One 
				Commissioner  asked  whether the solicitor had  
				moved the case along as quickly as it might have been .  
				The solicitor outlined the interminable process  of our 
				legal system.  ( A process that needs serious change . It 
				repeatedly   takes justice completely  out of the 
				equation  and makes "running people out of money " an 
				effective  tactic for winning.  So serious legal 
				reform in our community , state and nation  is indeed 
				another issue that challenges us ).The solicitor pointed out 
				that even if you endure the costs etc , and prevail, that you 
				still have to pay fair market value for the property .  A 
				resident pointed out that the costs have already included those 
				of a lawsuit for suppressing freedom of speech,  and that  
				our costs to get OUT of the eminent domain lawsuit will be in 6 
				figures  and that residents have been maligned in the 
				process as well. That maligning represents another unacceptable 
				cost of what our township considers acceptable procedure. 
   It was also pointed out that there are other buildings exist in 
				which to install a library - so it is not for want of a library 
				that all of that is being done.  And if we are installing  
				library branches, mightn't they be farther than 1 mile away?   
				Or instead of a several million dollar process 1 mile away , 
				perhaps many  small branches within walking distance of 
				many neighborhoods would be a better way to spend the money.  
				
                
          
				
                11-29-10  
				 The request for the extension 
				of the grant was not approved- what will happen now ? Is all 
				that money that was spent out the window? stay tuned...
				
                
				
                11-10   The 
				cost of this is climbing and climbing - into the millions. And 
				this at a time when crossing guards are being cut to trim the 
				budget . But we seem to have unlimited funds for this pet 
				project, no matter that flooding issues, road repairs etc have 
				to be put aside and while residents continue to express concern 
				at inadequate code enforcement measures that affect the quality 
				of their lives and the latest measures approved in the same 
				meeting that parents were turned down to have a crossing guard 
				at a dangerous five-point intersection. At the 11-04-10 Board of Commissioners meeting 
				(unlimited? ) funds to litigate were approved. Priority one, it 
				seems.
                
                
          
				
                
                 
          
                Background : 
                In Roslyn on Easton Rd, a former carpet store has remained 
                unrented for many (possibly over 20) years.  Residents would like to see a 
                thriving commercial area.  Township officials in early 09 
                voted to take this property by Eminent Domain, against the 
                wishes of the owner. There are mixed feeling about this 
                issue - Residents would like  a nice new, bigger library 
                facility and an arts and cultural center - and would like to see 
                vacant stores be transformed. Many others have come to the 
                podium to tell the Commissioners that the taking is wrong for so 
                many reasons . There is the fact that properties are available 
				for sale - so no "taking" is needed, the fact that one of the 
				best township libraries in the USA is a mile away, that fact 
				that other neighborhoods like Crestmont or McKinley might 
				benefit from a small "walk to " facility " if funds are so 
				plentiful and there is of course the fact that all the budget 
				cuts  mean funds are NOT available .   
                
                
				
                
                From the discussions I have had with residents,  few seem to know the real 
                details of what is involved in the process of such a taking .
      "Eminent domain" allows a property to 
                be taken by a governmental  entity for certain purposes.  The governmental 
                entity must reimburse what is determined to be the fair market 
                value.  This is obviously a very simplified 
                explanation.     The Township intends to 
                create "The  Roslyn Arts and Library Center" with this 
                property. Besides the purchase, there will be interior and 
                exterior improvements, parking enhancements and other costs.  
                The cost of the project was estimated at 1.9 million in May. The 
                cost of the litigation that has ensued, however, cannot be 
                calculated and was not in that figure.    
       The owner of this property has charged 
                that the taking  was not done properly, so litigation is 
                underway.  And in a separate suit, the owner has claimed 
                that if this piece is taken it will affect the value of the 
                entire strip, so the Township would , in their view, have 
                substantially more to reimburse as their loss is greater than 
                just this small section.  Residents have also raised their 
                voices to protest not just the cost, but also the manner in 
                which this has been done - including the fact that this came up 
                for a vote at a meeting when it was not even on the agenda - so 
                those who might have like to address the issue were not notified 
                to be in attendance. And a third action related to this issue 
                has now been disclosed regarding residents comments that were 
                curtailed as they sought to address this issue for the public 
                record,  for those who watch the meeting, and to their 
                Commissioners.  
 
    Besides the unknown expense,  issues have arisen about  
                the taking of someone's property when so many others lie vacant, 
                about the building of a Library just a mile away from a premiere 
                facility, about the manner in which the taking  was done and about the 
                fact that even the nearby neighbors   
                remain by-and- large unaware of all the details of the Township's 
                plan or how it will affect them.  Homes  on Avondale, 
                Independence, Lafayette and virtually all the streets behind this 
                property ( and  all the way up to Woodland)  have 
                been under discussion as to a possible zoning change. The minutes 
                of those meetings reflect a desire to zone some of these homes 
                for commercial uses . As of this writing, we have found few  who had 
                any idea these discussions were taking place.  (See the page 
                on zoning 
                rewrites for more info. )     
                The areas in question are along  Easton & 
                Bradfield Roads, particularly between Susquehanna and Woodland.  The Zoning Ordinance Re-write Committee 
                has this area listed as Transition Area 14  in their 
                minutes.   
       Because this is a complicated issue, being 
                notified after all the zoning recommendations are in place does 
                not seem  ideal.  If residents were encouraged to 
                attend the public 
                meetings now , do research, and begin to get up to speed, they 
                might understand enough to have meaningful comment in time to 
                effect change. Neighborhood 
                representatives at these meetings to take the news back to 
                others so they could participate in the shaping of this plan 
                would be an appropriate plan. 
                
                 
                
                ________________________ 
                CHRONOLOGY 
                11-4-10
                
                Litigation continues - approvals for funds given  
				
                9-30-09
                
                A speaker  shared  an example of Eminent Domain as 
                happened in the Coatesville area  that cost millions of dollars 
                in Litigation . He pointed out that besides the premier library 
                just about 1 mile away, that there also were many other 
                buildings that could house a Library & whose owners were not 
                protesting the sale. He urged the Commissioners not to drag 
                everyone into a legal battle . (Which we are already in with 
                multiple lawsuits)   
                 
                9-10-09
                
                  Commissioners seem to have taken the prior action to 
                heart and decided to allow the comments of both the Township 
                resident and the Montgomery County resident who asked to speak.  
          
                
                8-13-09 
                
                Commissioners were notified at the Board meeting tonight that 
                the below mentioned county resident &  township resident 
                were charging certain of the Commissioners with interfering in 
                their right to public comment . A copy of the documents re: the 
                lawsuit that was filed was 
                offered to them.  
                
                8-09 The owner files an additional lawsuit suggesting 
                that taking the portion of the  property devalues the rest 
                of the property owned and that additional compensation should be 
                due. 
                
                
                7-09   The owner of the property has responded to 
                the legal action of the taking and is prepared to fight this 
                action . At a meeting both  an Abington resident and a 
                Montgomery County resident were refused the opportunity to 
                speak.  The Abington resident had already been refused the 
                opportunity to speak at the County level, having been told he 
                should address at the township.  The Montgomery County 
                resident asked to speak because County grant monies were being 
                requested by Abington.  He was denied.  
                
                5-26-09 Township Assistant Manager Matt Lahaza went to the 
                County Revitalization Board to request funds. he informed the 
                board of the inadequacy of the library's present location and 
                explained the acquisition of 1180 Easton Rd . He said the 
                Township acquired the building through condemnation and is now 
                waiting for the appeal process to be completed.  Abington 
                Township is applying for a total of $352,192  of the county 
                revitalization funds in 2009 to renovate the exterior of the 
                building and property in three phases.  The cost of the 
                entire project was presented as estimated at 1.9 million. (Phase 1- the acquisition  quoted below at $640,000 does not 
                include the cost of any litigation - which we later learned was 
                filed)  . Phase 2 is exterior wall renovation - $127,154 requested 
                of county funds.   Phase 3 is performance stage and 
                seating . Anticipated completion of this area is December 2009.  $122,998 requested in county funds. And 
                Phase 4  
                is parking enhancements which include a parking tray along 
                Bradfield Road and additional parking spaces on the lot Bradfield Road.  The Township still needs to acquire a 
                3 
                to 4 foot wide strip of land as part of the parking tray not 
                included in the condemnation price.  Anticipated completion 
                of this is May 2010 .  $102,040 is requested in county funds 
                for this. 
                
                     Also discussed were other State County Township 
                and federal funds.  An Abington resident in attendance was not 
                allowed to speak, despite the fact that this was not 
                on the Abington agenda, where he was told he should address the 
                matter.  
                
                5-14-09 At the Board of Commissioners Meeting - the Eminent Domain 
                Issue on the Easton Rd property in Roslyn being taken against 
                the owner's wishes came up for a vote.  Despite not being 
                on the agenda,  this came up for a vote ---- and the vote passed. We 
                have not yet heard the legal opinion on that process, but I am 
                not sure why residents do not get to be alerted that there is 
                going to be a vote on this issue.  More 
                on this coming - check back .  
                
                In addition the cost of the acquisition of the property was 
                presented at the meeting  as $640,000 ----- even though one 
                Commissioner told us  that in Executive session right 
                before the meeting it was discussed that it was VERY UNLIKELY 
                that there was going to be any possibility of getting this 
                property for $640,000  and that the likelihood of  
                litigation could balloon the costs quite beyond this amount . 
                
                Despite it being a larger facility , the manager presented that 
                there would not be any increase in management costs and that the 
                library director had said they would maintain the same staffing 
                levels.  But later it was noted that, of course, the 
                costs alone of the much larger facility, increased HVAC costs, 
                etc. could not possibly make management costs the same - & how 
                could you increase the number of people you serve and add a 
                thriving "community center" without additional costs. Will 
                residents be forced to continue to accept this bad math from 
                Township personnel, without any supervision from the 
                commissioners ?  
                 
   BAD MATH  :  These two examples of  "bad 
                math"  from our  township  staff - presenting 
                things to the public that presents only half the picture or a 
                false picture - should not go unnoted by residents watching 
                their government. The tax abatements figures offered 3-08 provided a skewed view  of the actual 
                costs of abatement (forgetting to mention many figures that 
                dramatically affect the bottom line & therefore the actual 
                benefit).   At the end of 2008 we watched our manager in 
                a budget cuts session present lengthy explanations  to a 
                full room of people of what we would save if we cut certain 
                items ........and then tell us that these could not be cut.   
                Okay...... 
                We also heard in this current Eminent Domain session that there were 
                "low-ball figures" obtained  in prior eminent domain 
                dealings. Who is overseeing these operations?  And why are 
                we tolerating these things & allowing such shenanigans in the 
                operation  of our Township and the handling of our tax dollars?  In the 
                channel 43 dealings - residents comments and suggestions were 
                ignored to end up with  a substantially increased cost in 
                the taping of the meetings. This  is happening again and 
                again right before our eyes.  It is apparently at the 
                ballot box that we look for  elected officials that will 
                oversee the staff they have hired.  But who is choosing the 
                candidates for the elections?  
                
                An Eminent Domain question that might cry out for an answer :  If we were able to find this 
                owner for the taking of her property - why were we not looking 
                for her for the past 20 years when we needed to encourage her to 
                do something with the property to benefit the town?  
                Perhaps management could have more of an effect on improving 
                blighted areas than it currently is accomplishing.  
                
                __________________ 
				
                  
				
				
                   
				 
				Our codebook is in 2 parts
				
				
				 
				Part 1 
				  Township's 
				Codebook    
				except for  zoning 
				  
				
				Part 2
				
				Zoning Portion of Township Codebook
          
				
				or go to
				
				
				http://www.abingtonpa.gov/info/newcodebook.htm  
				
				
				
                
                
                
                  
                
                  
                
                  
                
                
          
                
                The Washington Post on Eminent Domain  http://www.washingtonpost.com/wp-dyn/content/article/2005/06/23/AR2005062300783.html?referrer=emailarticle
                
                
                
                
                  
          
                
                 
                 
                 
                __________________________ 
  
          
                
          
                
				  
                
          
                  
                
                
           
                 
          
                
                   
                
                
          
                
                 Please feel free to 
                
                contact us  
                with your own 
                 information on these topics  and please be sure 
                to    
                contact us 
                about any information you believe to be 
                incorrect -
                
                 
          
                
                
				  
          
          
				  
                
            
          
          
           | 
        
        
          | 
          
 
          
 
  
    
			  
Sign up here to receive our periodic Newsloop updates on issues that matter to us all. 
Knowledge is power. Stay informed to help shape your community and make a difference.
  
Abington Township revamped the entire Township website at the end of 2015
and broke all the links to the information. In 2017, under Richard 
Manfredi,  
someone inexperienced was assigned to redo the entire website again.
The public was not asked what problems they would like to see fixed. Their new plan was 
not well thought out, so everything was very hard to find and there were giant 
paragraphs you had to slog through in order to find the pertinent one or two 
lines that you needed. Or if you were lucky enough to even find the meetings and 
agenda page, there was (and still is) a whole page 
of nonsense on top, so you think you're on the wrong page. Zoom limks are 
burrid in a giant paragraph, so people can't find them to attend the meeting. 
They know about these  problems - but have just decided to ignore us.... 
for the whole of Richard Manfredi's time here (with Tom Hecker's consent).  
  Now, in 2025, we are due to get a new Manager, 
and there are funds put aside to, once again, upgrade the Township website. We can only hope for a 
fresh chance at fixing some of these things, as our Township website is the best tool we 
have for communication and should be an easy, user friendly site for all. 
  
We need volunteers willing to work together to help improve the Township site 
that everyone has to use,  to make it functional and accessible.  
  We will be repairing our broken links in this Abington Citizens site, 
too, and fixing some of our many, many 
typo's as much as is possible. (Yes, it's quite evident that, unlike the 
Township, WE don't have a paid staff of 275+ or a $93 million budget).
   
 So...please let us know if you find broken links 
or typos. Send us the URL  
and/or 
and the name of the page it is on, so we can correct it. 
Thanks for the help.
  
DISCLAIMER: 
 
 
The information in this site, like any site, may have unintentional inaccuracies. These pages also have opinions.
 Nothing should not be relied upon as fact until it is confirmed personally by the reader. 
 Please read our full 
Disclaimer
and read our Policies page before using 
this site. 
Again..... if you find inaccuracies or even grammatical errors,  please
contact us so we may correct them. 
			    
              |